13 August 2007
BT asserts delivery of two milestones
BT asserted on 3 July that it had delivered two significant Undertakings milestones: Wholesale Line Rental Ready for Service (WLR RFS) and the implementation of Operational Support Systems (OSS) user access controls in Openreach for certain EoI products. The EAB has begun its validation of both milestones and will report the outcome in a future Overview.
WLR RFS
Despite some challenges, BT nevertheless believes it achieved the WLR RFS milestone. The EAB noted that BT would be making payments during July 2007 to the relevant CPs in case it needed to revert to fallback systems in the month. BT notified the EAB that it had used this fallback option during July and had been in breach as a result (see the final breach notification below). However, since 1 August BT states that it has returned to an EoI service in compliance with the Undertakings requirements. The EAB will continue to monitor this situation on an ongoing basis as well as completing its usual validation process.
OSS variation
Following a consultation, on 21 June 2007 Ofcom published a variation to the Undertakings regarding the separation of Openreach's OSS from the rest of BT. The variation commits BT to meet milestones on the way to full physical separation in 2010. In the interim, BT is required to put in place user access controls for specified key EoI products supported on shared systems during 2007/08, which it asserted that it had delivered from 30 June 2007. The EAB is validating BT's delivery of these interim measures, and it is also required to commission an internal audit on BT's progress towards delivery of full physical separation in 2010.
EAB validations
The EAB's validation work on a number of other milestones continues:
Complaint from a CP
On 11 May 2007, the EAB received a complaint from a CP ”which requested to remain anonymous ”alleging that Openreach supplied dark fibre to BT CPs in contravention of the Undertakings provisions regarding Openreach's product portfolio. The EAO found that since the downstream product offered by BT Global Services was covered by a variation of the Undertakings (pending the outcome of discussions with Ofcom in relation to a requested exemption from EoI), no breach had occurred. As a result, the EAB did not uphold the complaint.
Six breaches of the Undertakings reported
BT reported six breaches of the Undertakings to the EAB at its July meeting. This brings the total number of breach notifications that the EAB has received from BT to 17 since the Undertakings were agreed. The EAB assesses BT's classification of breaches and monitors any remedial action taken by BT following a breach of the Undertakings.
One of the breaches reported at the EAB's July meeting was non-trivial, three were trivial and two are still to be classified.
The non-trivial breach was:
The trivial breaches were:
The breaches yet to be classified were:
Virgin Media attends July EAB meeting
Andy King, Director of Regulation and Compliance at Virgin Media, attended the EAB's July meeting to discuss next generation networks and BT's Consult 21 programme. Further industry attendees are planned for EAB meetings during the rest of 2007.
Glossary
BES: Backhaul Extension Services
CCI: Customer Confidential Information
Consult21: BT's consultation on its next generation network plans
CPs: Communications Providers
EoI: Equivalence of Inputs
IBMC: Installed Base Migration Complete
ISDN: Integrated Services Digital Network
LLU: Local Loop Unbundling
OSS: Operational Support Systems
PSTN: Public Switched Telephony Network
RFS: Ready for Service
WES: Wholesale Extension Services
WLR: Wholesale Line Rental
Links